Latest Important Updates
The multipurpose Jamrani Dam Project is progressing under the supervision of the Uttarakhand Irrigation Department, with the overall project completion target set for June 2032. Construction work on one major diversion tunnels has reportedly completed and second has reportedly reached around 85% completion. These tunnels are being developed to divert river flow and accelerate the permanent dam construction process before the monsoon season.
Meeting with ADM related to R&R works at Nainital